Date
May 2012
Location
Gould Crescent, Christchurch
Principal
Stronger Christchurch Infrastructure Rebuild Team (SCIRT)
Contractor
Worthington Contractors

Damage from the February 2011 earthquake badly affected a number of Christchurch city’s pump stations for waste and fresh water with repairs taking many months to complete. With regular large aftershocks part of the landscape in Christchurch, what would the city do should another large earthquake once again damage pump stations? A contingency plan was urgently required with Josh and James Worthington from Worthington Contractors tasked with installing a backup system.

“We were contracted by SCIRT to install an overflow weir system - which is a gravity based sewer system - on Gould Crescent next to Heathcote Estuary so that, should the pump station be damaged in future, a backup system would take the sewage away from residential areas,” says Josh Worthington, Director of Worthington Contractors.

With earthquakes rattling the city on a daily basis speed was imperative for the installation. “We had three weeks to install the back up system in difficult conditions due to poor soil conditions and a high water table. We had intended using sheet piling to shore the sides of the trench but Frank from Trench Shoring New Zealand had previously introduced me to the benefits of the single rail shoring system and due to the availability of equipment, the timing of the project and the difficult conditions we saw this as an ideal opportunity to trial this system.”

Josh discovered by using Trench Shoring’s single rail system that the installation rate was far higher than using a sheet piling system. “This system was quick to install and was readily available - which suited this situation perfectly,” adds Josh. “Everything went very well and we finished the project within the set timeframes.”

single_slide_system_04_

How was this achieved?

Trench Shoring New Zealand’s single corner slide rail system was used to create a manhole with the shoring system installed as work progressively pushed into the excavation. Due to the high water table the manhole also required de-watering during the installation. A single parallel slide rail shoring with an inside width 1.5m was then installed linking the existing manhole to the new manhole. Four modules of slide rail with a combination of 3m and 4m long panels were used to achieve the required length of shoring between the manholes. Once installed the transverse frame assemblies were raised in their slides to enable the pipe to be introduced into the trench in one length. The final 6m length of pipe was installed to the outfall using the single parallel slide rail.

The single slide rail system enables safe and efficient excavation to an effective depth of 4m in almost all soil conditions.

single_slide_system_02_ single_slide_system_03_